Location: Northern Manitoba
​
Description: Foundation Installation, Camp set-up & maintenance, Clearing Right of Way, Road Construction & Maintenance, Trucking
​
Completion Date: Winter 2015
​
Owner: Manitoba Hydro
​
The Bipole III Transmission Line N1 section runs from the Burntwood River northeast of Thompson, MB up to Keewatinohk Generating Station northeast of Gillam, MB.
​
The work involved the set up and full service of the remote camp to accomodate the workforce. As well as the road construction and maintenance of access roads, the right of way and ice crossings. A large portion of the work was the clearing of the transmission line and testing of the ground at the tower sites and then the installation of the appropriate anchors and foundations.